The Tanner Building is undergoing a five-year construction process. Updates and building navigational tools are available here.
Construction News
5-Year Schedule
| Project Start | Location | Affected Units | Expected Completion |
|---|---|---|---|
| Spring 2026 | 4th Floor South | Marketing & Communication, Mental Health & Wellbeing, Undergraduate Advisement | August 2026 |
| Spring 2026 | 3rd Floor South | Ballard Center, Global Business Center, Technology | October 2026 |
| Fall 2026 | 3rd Floor North | Behavioral Research Lab, Graduate lounges | December 2026 |
| Winter 2027 | 1st, 2nd 3rd Floor Atriums | Hosting spaces | April 2027 |
| Spring 2027 | 2nd Floor North | Classrooms | August 2027 |
| Fall 2027 | 7th Floor South | Information Systems | December 2027 |
| Winter 2028 | 7th Floor North | Operations | April 2027 |
| Spring 2028 | 1st Floor North | Classrooms | August 2028 |
| Fall 2028 | 6th Floor South | Marketing & Global Supply Chain | December 2028 |
| Winter 2029 | 6th Floor North | Finance | April 2029 |
| Spring 2029 | 4th Floor North | Business Career Center | August 2029 |
| Fall 2029 | 5th Floor South | Management | December 2029 |
| Winter 2030 | 5th Floor North | Accounting | April 2030 |
| Spring 2030 | 2nd Floor South | Classrooms | August 2030 |
| Fall 2030 | TBD | TBD | December 2030 |
| Winter 2031 | TBD | TBD | April 2031 |
| Spring 2031 | 1st Floor South | Classrooms | August 2031 |